Vaidya West World - Serenity, Andheri East

by Vaidya Spaces Private Limited · Andheri East, Mumbai 400069 · Map

Launched
Apr 20243 yrs 4 mths promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
16 of 2857% · 15 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 28 units

Rehab15 units for existing members

Land-owner share1 unit, not for sale

Total 44 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
9
2 BHK
9
3 BHK
17
Other units
9
Total units
44
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
15
Land-owner share (not for sale)
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%16
100%0%0%0
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vaidya West World - Serenity by Vaidya Spaces Private Limited is a 44-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in April 2024 with possession due in August 2027. 16 units booked out of 28 units for sale. The concrete structure (RCC) is complete.

Read full summary

Vaidya West World - Serenity is a BMC-sanctioned project by Vaidya Spaces Private Limited in Andheri East, Mumbai 400069, registered with MahaRERA as P51800055855. It was launched in April 2024. It has 44 units in 1 building: 35 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 28 are for sale, 15 are rehab units for existing members and 1 is the land-owner's share, not for sale.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

16 units booked out of 28 units for sale (57%). Since the July 2026 update, 16 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.