Prabhu Krupa, Vile Parle West
Ready to move
by Mehul Kirit Mehta · Vile Parle West, Mumbai 400056 · Map
- Launched
- May 20243 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 4 of 1625% · 13 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 16 units
Rehab13 units for existing members
Total 29 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 3
- 3 BHK
- 24
- 5+ BHK
- 1
- Total units
- 29
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 16
- Rehab units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 4 | |
| 100% | 40% | 0% | – | |
| 100% | 40% | 0% | – | |
| 100% | 10% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400056
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 7 mths | 2 yrs 6 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Sep 2026 |
| Concrete structure (RCC) | 100% | 95% |
| Units booked (free sale) | 25% | 45% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Vatika Sudarsan, Vile Parle West
- Shanti Sadan, Vile Parle West
- Avasva Aarambh, Vile Parle West
- Sudarsan Enclave, Vile Parle West
- Shriniketan, Vile Parle West
- Kuber Villa, Vile Parle West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vatika Sudarsan | May 2024 | June 2026 | 100% | 11 units booked out of 11 units for sale |
| Shanti Sadan | May 2024 | December 2026 | 90% | 4 units booked out of 9 units for sale |
| Avasva Aarambh | April 2024 | December 2027 | 0% | 6 units booked out of total 59 units |
| Sudarsan Enclave | March 2024 | April 2026 | 100% | 5 units booked out of 11 units for sale |
| Shriniketan | February 2024 | December 2026 | 42% | 2 units booked out of 12 units for sale |
| Kuber Villa | February 2024 | June 2026 | 100% | 15 units booked out of total 15 units |
About this project
Prabhu Krupa by Mehul Kirit Mehta is a 29-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in May 2024 with possession due in December 2027. 4 units booked out of 16 units for sale. The concrete structure (RCC) is complete.
Read full summary
Prabhu Krupa is a BMC-sanctioned project by Mehul Kirit Mehta in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800055997. It was launched in May 2024. It has 29 units in 1 building, with 1, 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 16 are for sale and 13 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
4 units booked out of 16 units for sale (25%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 40% to 100%.