Skip to main content

Sejal Square, Goregaon East

by Alchemi Developers Private Limited · Goregaon East, Mumbai 400063 · Map

Launched
May 20245 yrs 7 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked
230 of 29678% · 225 in Jul 2026
Buildings
10.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
296
Total units
296
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 10%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%230
100%0%0%225
10%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sejal Square by Alchemi Developers Private Limited is a 296-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in May 2024 with possession due in December 2029. 230 units booked out of total 296 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sejal Square is an SRA-sanctioned project by Alchemi Developers Private Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800056052. It was launched in May 2024. It has 296 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

230 units booked out of total 296 units (78%). Since the July 2026 update, 5 more units have been booked.