by Trustworth Realtech Private Limited · Malad West, Mumbai 400064 · Map

Launched
May 20244 yrs 7 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
57
Total units
57
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation60%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 60%Dec 2025: Excavation 60%Jul 2026: Excavation 60%Oct 2026: Excavation 60%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 60%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
60%0%0%–
60%0%0%–
60%0%0%–
60%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Trustworth Malad by Trustworth Realtech Private Limited is a 57-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in May 2024 with possession due in December 2028. Work on the concrete structure (RCC) has not started.

Read full summary

Trustworth Malad is a BMC-sanctioned project by Trustworth Realtech Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800056138. It was launched in May 2024. It has 57 units in 2 buildings, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation 60% complete, structure (RCC) not started, final finishes not started.