Skip to main content

Goyal Nrupa Square, Borivali West

by Parshwa Amrit · Borivali West, Mumbai 400091 · Map

Launched
May 20242 yrs 10 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
30 of 5951%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale30 booked out of 59 units

Land-owner share1 unit, not for sale

Total 60 units. Land-owner units are not for sale.

Project facts

Other units
60
Total units
60
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
59
Land-owner share (not for sale)
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%30
100%10%0%29
100%10%0%21
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Goyal Nrupa Square by Parshwa Amrit is a 60-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in May 2024 with possession due in March 2027. 30 units booked out of 59 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Goyal Nrupa Square is a BMC-sanctioned project by Parshwa Amrit in Borivali West, Mumbai 400091, registered with MahaRERA as P51800056191. It was launched in May 2024. It has 60 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 60 units, 59 are for sale and 1 is the land-owner's share, not for sale.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

30 units booked out of 59 units for sale (51%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 10% to 60%.