Horizon Tower, Andheri East
by I.R.Developers LLP · Andheri East, Mumbai 400093 · Map
- Launched
- May 20241 yr 10 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 5 of 1338% · 12 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 13 units
Rehab12 units for existing members
Total 25 units. Rehab units are not for sale.
Project facts
- 3 BHK
- 25
- Total units
- 25
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 5 | |
| 100% | 100% | 0% | 2 | |
| 100% | 75% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Horizon Tower by I.R.Developers LLP is a 25-unit BMC-sanctioned project in Andheri East, Mumbai 400093, launched in May 2024 with possession due in March 2027. 5 units booked out of 13 units for sale. The concrete structure (RCC) is complete.
Read full summary
Horizon Tower is a BMC-sanctioned project by I.R.Developers LLP in Andheri East, Mumbai 400093, registered with MahaRERA as P51800056381. It was launched in May 2024. It has 25 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 13 are for sale and 12 are rehab units for existing members.
Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes not started.
5 units booked out of 13 units for sale (38%). Since the July 2026 update, 3 more units have been booked.