Sayba Signature Spaces, Goregaon East

Ready to move

by Star Sapphire · Goregaon East, Mumbai 400063 · Map

Launched
Jun 20243 yrs promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
45 of 7362% · 73 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale45 booked out of 73 units

Rehab73 units for existing members

Total 146 units. Rehab units are not for sale.

Project facts

1 BHK
62
Other units
84
Total units
146
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
73
Rehab units
73

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 68%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%45
100%100%68%45
100%100%50%43
100%40%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400063

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Jun 2027Dec 2027
Concrete structure (RCC)100%76%
Units booked (free sale)62%88%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Sayba Signature Spaces by Star Sapphire is a 146-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in June 2024 with possession due in June 2027. 45 units booked out of 73 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sayba Signature Spaces is an SRA-sanctioned project by Star Sapphire in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800056477. It was launched in June 2024. It has 146 units in 2 buildings: 62 homes (1 BHK) and 84 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 146 units, 73 are for sale and 73 are rehab units for existing members.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

45 units booked out of 73 units for sale (62%).