Girnar Residency Wing B Phase 1, Andheri East
by Nidhaan Realty LLP · Andheri East, Mumbai 400069 · Map
- Launched
- Jun 20242 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 25 of 6837% · 21 in Jul 2026
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 16
- 2 BHK
- 52
- Total units
- 68
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 25 | |
| 100% | 100% | 0% | 21 | |
| 100% | 94% | 0% | 9 | |
| 100% | 15% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Girnar Residency Wing B Phase 1 by Nidhaan Realty LLP is a 68-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in June 2024 with possession due in December 2026. 25 units booked out of total 68 units. The concrete structure (RCC) is complete.
Read full summary
Girnar Residency Wing B Phase 1 is a BMC-sanctioned project by Nidhaan Realty LLP in Andheri East, Mumbai 400069, registered with MahaRERA as P51800056491. It was launched in June 2024. It has 68 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
25 units booked out of total 68 units (37%). Since the July 2026 update, 4 more units have been booked.