Chandralok Chs Ltd, Mulund West

by Avion Developers · Mulund West, Mumbai 400080 · Map

Launched
Jun 20243 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
93%Mid-construction
Booked (free sale)
–No units for sale
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free saleNo units for sale

Rehab1 unit for existing members

Total 1 unit. Rehab units are not for sale.

Project facts

2 BHK
1
Total units
1
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
0
Rehab units
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)93%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 93%Oct 2026: Concrete structure (RCC) 93%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 93%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%0%0
100%93%0%0
100%0%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Chandralok Chs Ltd by Avion Developers is a 1-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in June 2024 with possession due in December 2027. No units for sale: rehab units only. The concrete structure (RCC) is 93% complete.

Read full summary

Chandralok Chs Ltd is a BMC-sanctioned project by Avion Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800076651. It was launched in June 2024. It has 1 unit in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 1 unit, none is for sale and 1 is a rehab unit for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 93% complete, final finishes not started.

No units for sale: rehab units only.