Vira Avenue, Vile Parle East

by Vira Realty India Private Limited · Vile Parle East, Mumbai 400057 · Map

Launched
Jun 20242 yrs 6 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked
29 of 8534% · 28 in Jul 2026
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
14
1 BHK
59
2 BHK
11
Other units
1
Total units
85
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 20%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%29
100%95%20%28
100%0%0%6
50%0%0%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400057

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths4 yrs 6 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2026Nov 2028
Concrete structure (RCC)100%92%
Units booked34%59%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Vira Avenue by Vira Realty India Private Limited is an 85-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in June 2024 with possession due in December 2026. 29 units booked out of total 85 units. The concrete structure (RCC) is complete.

Read full summary

Vira Avenue is a BMC-sanctioned project by Vira Realty India Private Limited in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800076751. It was launched in June 2024. It has 85 units in 2 buildings: 84 homes (1 RK, 1 BHK and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

29 units booked out of total 85 units (34%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 95% to 100%.