Brindavan Chsl, Dahisar

by Mitesh Bhikhubhai Shah · Dahisar, Mumbai 400068 · Map

Launched
Jun 20242 yrs originally promised
Possession (MahaRERA)
Oct 2028Extended by 2 yrs 4 mths
Concrete structure
75%Mid-construction
Booked
–
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 75%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%–
100%75%0%–
100%5%0%–
100%5%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Brindavan Chsl by Mitesh Bhikhubhai Shah is a BMC-sanctioned project in Dahisar, Mumbai 400068, launched in June 2024 with possession due in October 2028. The concrete structure (RCC) is 75% complete.

Read full summary

Brindavan Chsl is a BMC-sanctioned project by Mitesh Bhikhubhai Shah in Dahisar, Mumbai 400068, registered with MahaRERA as P51800076772. It was launched in June 2024. Its MahaRERA status is Active.

Its registered possession date is October 2028, extended by 2 years 4 months from the original June 2026. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.