Amalfi, Versova
by Richfeel Real Estate Pvt Ltd · Versova, Mumbai 400061 · Map
- Launched
- Jun 20243 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 21 of 2778% · 18 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 27 units
Rehab18 units for existing members
Total 45 units. Rehab units are not for sale.
Project facts
- 3 BHK
- 21
- 4 BHK
- 23
- Other units
- 1
- Total units
- 45
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 27
- Rehab units
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 21 | |
| 100% | 0% | 0% | 16 | |
| 50% | 0% | 0% | 0 | |
| 30% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Amalfi by Richfeel Real Estate Pvt Ltd is a 45-unit SRA-sanctioned project in Versova, Mumbai 400061, launched in June 2024 with possession due in December 2027. 21 units booked out of 27 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Amalfi is an SRA-sanctioned project by Richfeel Real Estate Pvt Ltd in Versova, Mumbai 400061, registered with MahaRERA as P51800076774. It was launched in June 2024. It has 45 units in 1 building: 44 homes (3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 45 units, 27 are for sale and 18 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
21 units booked out of 27 units for sale (78%). Since the July 2026 update, 5 more units have been booked.