Malhar Malti, Mulund West

by Atlanta Developers · Mulund West, Mumbai 400080 · Map

Launched
Jun 20242 yrs 9 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
20 of 2677% · 10 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 26 units

Rehab10 units for existing members

Total 36 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
20
2 BHK
9
3 BHK
2
Other units
4
Total units
36
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
26
Rehab units
10
Reserved units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%20
0%0%0%20
0%0%0%20
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths3 yrs 6 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Mar 2027Nov 2027
Concrete structure (RCC)0%84%
Units booked (free sale)77%63%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Malhar Malti by Atlanta Developers is a 36-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in June 2024 with possession due in March 2027. 20 units booked out of 26 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Malhar Malti is an SRA-sanctioned project by Atlanta Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800076824. It was launched in June 2024. It has 36 units in 1 building: 32 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 26 are for sale and 10 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

20 units booked out of 26 units for sale (77%).