Vaishno Sky, Malad East
by Shree Vaishno Homes Pvt ltd · Malad East, Mumbai 400097 · Map
- Launched
- Jul 20244 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 33%Mid-construction
- Booked (free sale)
- 52 of 13339% · 197 rehab units
- Buildings
- 20.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale52 booked out of 133 units
Rehab197 units for existing members
Total 330 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 190
- 2 BHK
- 81
- Other units
- 59
- Total units
- 330
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 133
- Rehab units
- 197
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 33% | 0% | 52 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400097
Projects with 100–600 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 5 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2028 | Dec 2027 |
| Concrete structure (RCC) | 33% | 80% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Proposed Bldg on Plot CTS No. 827 B, S.No. 239, in betn Shivneri CHS MCGM Pumphouse, Khadakpada, Malad East
- Cosmic Residency, Malad East
- Sigma Solitaire, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Proposed Bldg on Plot CTS No. 827 B, S.No. 239, in betn Shivneri CHS MCGM Pumphouse, Khadakpada | August 2024 | September 2025 | 80% | – |
| Cosmic Residency | January 2025 | December 2028 | 0% | 1 unit booked out of 98 units for sale |
| Sigma Solitaire | December 2023 | December 2027 | 100% | 157 units booked out of total 236 units |
About this project
Vaishno Sky by Shree Vaishno Homes Pvt ltd is a 330-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in July 2024 with possession due in December 2028. 52 units booked out of 133 units for sale. The concrete structure (RCC) is 33% complete.
Read full summary
Vaishno Sky is an SRA-sanctioned project by Shree Vaishno Homes Pvt ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800076925. It was launched in July 2024. It has 330 units in 2 buildings: 271 homes (1 and 2 BHK) and 59 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 330 units, 133 are for sale and 197 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 33% complete, final finishes not started.
52 units booked out of 133 units for sale (39%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 33%.