Sri Savaa, Goregaon West
by Avisa Nextgen Construction LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- Jul 20242 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr
- Concrete structure
- 54%Mid-construction
- Booked (free sale)
- 17 of 2959% · 12 rehab units
- Buildings
- 10.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale17 booked out of 29 units
Rehab12 units for existing members
Total 41 units. Rehab units are not for sale.
Project facts
- Other units
- 41
- Total units
- 41
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 29
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 54% | 24% | 17 | |
| 100% | 14% | 0% | 17 | |
| 100% | 14% | 0% | 5 | |
| 90% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sri Savaa by Avisa Nextgen Construction LLP is a 41-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in July 2024 with possession due in December 2027. 17 units booked out of 29 units for sale. The concrete structure (RCC) is 54% complete.
Read full summary
Sri Savaa is a BMC-sanctioned project by Avisa Nextgen Construction LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800077068. It was launched in July 2024. It has 41 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 41 units, 29 are for sale and 12 are rehab units for existing members.
Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction: excavation complete, structure (RCC) 54% complete, final finishes 24% complete.
17 units booked out of 29 units for sale (59%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 14% to 54%.