Sheth Square, Goregaon East

by Sheth Builders Private Limited · Goregaon East, Mumbai 400063 · Map

Launched
Jul 20244 yrs 10 mths promised
Possession (MahaRERA)
May 2029Not extended
Concrete structure
20%Mid-construction
Booked (free sale)
12 of 4726% · 21 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale12 booked out of 47 units

Rehab21 units for existing members

Total 68 units. Rehab units are not for sale.

Project facts

Other units
68
Total units
68
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
47
Rehab units
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)20%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 20%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 20%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%12
100%0%0%10
100%0%0%4
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sheth Square by Sheth Builders Private Limited is a 68-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in July 2024 with possession due in May 2029. 12 units booked out of 47 units for sale. The concrete structure (RCC) is 20% complete.

Read full summary

Sheth Square is an SRA-sanctioned project by Sheth Builders Private Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800077126. It was launched in July 2024. It has 68 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 68 units, 47 are for sale and 21 are rehab units for existing members.

Its registered possession date is May 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.

12 units booked out of 47 units for sale (26%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 20%.