Esquina Private Residence, Jogeshwari West
by Prabhakar Kunte Co Operative Housing Society Limited · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Jul 20244 yrs 11 mths promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 10 of 2148% · 0 in Dec 2025
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 12
- Other units
- 9
- Total units
- 21
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 10 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Esquina Private Residence by Prabhakar Kunte Co Operative Housing Society Limited is a 21-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in July 2024 with possession due in June 2029. 10 units booked out of total 21 units. The concrete structure (RCC) is complete.
Read full summary
Esquina Private Residence is a BMC-sanctioned project by Prabhakar Kunte Co Operative Housing Society Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800077147. It was launched in July 2024. It has 21 units in 1 building: 12 homes (3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
10 units booked out of total 21 units (48%). Since the December 2025 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.