Kalpataru Virtus, Vikhroli

by Mehal Enterprise LLP · Vikhroli, Mumbai 400083 · Map

Launched
Jul 20245 yrs 5 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
40%Mid-construction
Booked
130 of 25850% · 124 in Jul 2026
Buildings
11.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
258
Total units
258
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)40%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 20%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 40%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 40%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%130
50%0%0%124
50%0%0%–
20%0%0%65

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Kalpataru Virtus by Mehal Enterprise LLP (Kalpataru) is a 258-unit BMC-sanctioned project in Vikhroli, Mumbai 400083, launched in July 2024 with possession due in December 2029. 130 units booked out of total 258 units. The concrete structure (RCC) is 40% complete.

Read full summary

Kalpataru Virtus is a BMC-sanctioned project by Mehal Enterprise LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800077219. It was launched in July 2024. It has 258 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.

130 units booked out of total 258 units (50%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 40%.

Kalpataru's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA42
Total units across these projects6,678
Completed without extending the possession date19
Completed after an extension8
Lapsed0
Under construction15
Possession date extended on the builder's application9
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Kalpataru projects225 (21 of 42 projects)