Green Shadow CHSL, Andheri East

by Green Globe Realty · Andheri East, Mumbai 400099 · Map

Launched
Aug 20242 yrs 4 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
7 of 888% · 10 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 8 units

Rehab10 units for existing members

Total 18 units. Rehab units are not for sale.

Project facts

2 BHK
16
3 BHK
2
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
8
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 15%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%7
100%100%15%6
100%80%0%4
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Green Shadow CHSL by Green Globe Realty is an 18-unit BMC-sanctioned project in Andheri East, Mumbai 400099, launched in August 2024 with possession due in December 2026. 7 units booked out of 8 units for sale. The concrete structure (RCC) is complete.

Read full summary

Green Shadow CHSL is a BMC-sanctioned project by Green Globe Realty in Andheri East, Mumbai 400099, registered with MahaRERA as P51800077271. It was launched in August 2024. It has 18 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 8 are for sale and 10 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

7 units booked out of 8 units for sale (88%). Since the July 2026 update, 1 more unit has been booked.