HS One, Mulund West

by HS Lifespace LLP · Mulund West, Mumbai 400080 · Map

Launched
Aug 20243 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
88%Mid-construction
Booked (free sale)
61 of 12848% · 29 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale61 booked out of 128 units

Rehab29 units for existing members

Total 157 units. Rehab units are not for sale.

Project facts

Other units
157
Total units
157
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
128
Rehab units
29

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)88%
Finishes, lifts and services5%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 88%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 5%Excavation 100%Concrete structure (RCC) 88%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%88%5%61
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

HS One by HS Lifespace LLP is a 157-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in August 2024 with possession due in December 2027. 61 units booked out of 128 units for sale. The concrete structure (RCC) is 88% complete.

Read full summary

HS One is an SRA-sanctioned project by HS Lifespace LLP in Mulund West, Mumbai 400080, registered with MahaRERA as P51800077285. It was launched in August 2024. It has 157 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 157 units, 128 are for sale and 29 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 88% complete, final finishes 5% complete.

61 units booked out of 128 units for sale (48%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 88%.