Hanuman Nagar Azad Nagar Sra Chs, Goregaon East

by Pratha Constructions · Goregaon East, Mumbai 400063 · Map

Launched
Aug 20245 yrs 4 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked
32 of 25013% · 28 in Jul 2026
Buildings
11 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
58
2 BHK
192
Total units
250
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%32
100%0%0%28
75%0%0%23
75%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400063

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths5 yrs 2 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2029Dec 2029
Concrete structure (RCC)0%53%
Units booked13%57%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Hanuman Nagar Azad Nagar Sra Chs by Pratha Constructions is a 250-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in August 2024 with possession due in December 2029. 32 units booked out of total 250 units. Work on the concrete structure (RCC) has not started.

Read full summary

Hanuman Nagar Azad Nagar Sra Chs is an SRA-sanctioned project by Pratha Constructions in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800077345. It was launched in August 2024. It has 250 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

32 units booked out of total 250 units (13%). Since the July 2026 update, 4 more units have been booked.