Kalpataru Advay, Borivali West

by Kalpataru Limited · Borivali West, Mumbai 400091 · Map

Launched
Aug 20245 yrs 10 mths promised
Possession (MahaRERA)
Jun 2030Not extended
Concrete structure
72%Mid-construction
Booked (free sale)
243 of 33173% · 445 rehab units
Buildings
35.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale243 booked out of 331 units

Rehab445 units for existing members

Total 776 units. Rehab units are not for sale.

Project facts

1 BHK
7
2 BHK
415
3 BHK
274
4 BHK
78
5+ BHK
2
Total units
776
Buildings
3
Land
5.9 acres
Phases
1
MahaRERA complaints
0
Free-sale units
331
Rehab units
445

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 36%Oct 2026: Concrete structure (RCC) 72%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 72%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%0%243
100%36%0%213
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Kalpataru Advay by Kalpataru Limited is a 776-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in August 2024 with possession due in June 2030. 243 units booked out of 331 units for sale. The concrete structure (RCC) is 72% complete.

Read full summary

Kalpataru Advay is a BMC-sanctioned project by Kalpataru Limited in Borivali West, Mumbai 400091, registered with MahaRERA as P51800077381. It was launched in August 2024. It has 776 units in 3 buildings, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 776 units, 331 are for sale and 445 are rehab units for existing members.

Its registered possession date is June 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 72% complete, final finishes not started.

243 units booked out of 331 units for sale (73%). Since the July 2026 update, 30 more units have been booked and the reported concrete structure (RCC) has gone from 36% to 72%.

Kalpataru's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA42
Total units across these projects6,678
Completed without extending the possession date19
Completed after an extension8
Lapsed0
Under construction15
Possession date extended on the builder's application9
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Kalpataru projects225 (21 of 42 projects)