Kalpataru Advay, Borivali West
by Kalpataru Limited · Borivali West, Mumbai 400091 · Map
- Launched
- Aug 20245 yrs 10 mths promised
- Possession (MahaRERA)
- Jun 2030Not extended
- Concrete structure
- 72%Mid-construction
- Booked (free sale)
- 243 of 33173% · 445 rehab units
- Buildings
- 35.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale243 booked out of 331 units
Rehab445 units for existing members
Total 776 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 7
- 2 BHK
- 415
- 3 BHK
- 274
- 4 BHK
- 78
- 5+ BHK
- 2
- Total units
- 776
- Buildings
- 3
- Land
- 5.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 331
- Rehab units
- 445
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 72% | 0% | 243 | |
| 100% | 36% | 0% | 213 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Kalpataru Advay by Kalpataru Limited is a 776-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in August 2024 with possession due in June 2030. 243 units booked out of 331 units for sale. The concrete structure (RCC) is 72% complete.
Read full summary
Kalpataru Advay is a BMC-sanctioned project by Kalpataru Limited in Borivali West, Mumbai 400091, registered with MahaRERA as P51800077381. It was launched in August 2024. It has 776 units in 3 buildings, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 776 units, 331 are for sale and 445 are rehab units for existing members.
Its registered possession date is June 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 72% complete, final finishes not started.
243 units booked out of 331 units for sale (73%). Since the July 2026 update, 30 more units have been booked and the reported concrete structure (RCC) has gone from 36% to 72%.
Kalpataru's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 42 |
|---|---|
| Total units across these projects | 6,678 |
| Completed without extending the possession date | 19 |
| Completed after an extension | 8 |
| Lapsed | 0 |
| Under construction | 15 |
| Possession date extended on the builder's application | 9 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Kalpataru projects | 225 (21 of 42 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.