Isle Of Calm, Powai

by Sunrise Housing · Powai, Mumbai 400076 · Map

Launched
Aug 2024First of 2 phases
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
36%Weighted across 2 phases
Booked
217 of 32068% · 167 in Jul 2026
Buildings
23.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
95
2 BHK
203
3 BHK
20
Other units
2
Total units
320
Buildings
2
Land
3.1 acres
Phases
2
MahaRERA complaints
0
Reserved units
30

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Isle Of Calm Tower 2
Mid-construction
P5180007740114025%79%
Isle Of Calm Tower 1
Mid-construction
P5180007792217845%59%
Show updates by phase

Isle Of Calm Tower 2 (P51800077401)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%110
100%10%0%75
100%0%0%75
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Isle Of Calm Tower 1 (P51800077922)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%107
100%13%0%92
100%0%0%27
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)36%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 12%Oct 2026: Concrete structure (RCC) 36%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 36%Final finishes 0%

How to read construction stages

About this project

Isle Of Calm by Sunrise Housing is a 320-unit BMC-sanctioned project in Powai, Mumbai 400076, registered with MahaRERA in 2 phases, with possession due in March 2029. 217 units booked out of total 320 units. The concrete structure (RCC) is 36% complete.

Read full summary

Isle Of Calm is a BMC-sanctioned project by Sunrise Housing in Powai, Mumbai 400076, registered with MahaRERA as 2 phases (P51800077401, P51800077922). The first phase was launched in August 2024. Together the phases have 320 units in 2 buildings: 318 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The registered possession date is March 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 36% complete and final finishes 0% complete. Neither phase has its structure complete.

217 units booked out of total 320 units (68%). Since the July 2026 update, 50 more units have been booked.