Isle Of Calm, Powai
by Sunrise Housing · Powai, Mumbai 400076 · Map
- Launched
- Aug 2024First of 2 phases
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 36%Weighted across 2 phases
- Booked
- 217 of 32068% · 167 in Jul 2026
- Buildings
- 23.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 95
- 2 BHK
- 203
- 3 BHK
- 20
- Other units
- 2
- Total units
- 320
- Buildings
- 2
- Land
- 3.1 acres
- Phases
- 2
- MahaRERA complaints
- 0
- Reserved units
- 30
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Isle Of Calm Tower 2 Mid-construction | P51800077401 | 140 | 25% | 79% | |
| Isle Of Calm Tower 1 Mid-construction | P51800077922 | 178 | 45% | 59% |
Show updates by phase
Isle Of Calm Tower 2 (P51800077401)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 25% | 0% | 110 | |
| 100% | 10% | 0% | 75 | |
| 100% | 0% | 0% | 75 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Isle Of Calm Tower 1 (P51800077922)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 107 | |
| 100% | 13% | 0% | 92 | |
| 100% | 0% | 0% | 27 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Isle Of Calm by Sunrise Housing is a 320-unit BMC-sanctioned project in Powai, Mumbai 400076, registered with MahaRERA in 2 phases, with possession due in March 2029. 217 units booked out of total 320 units. The concrete structure (RCC) is 36% complete.
Read full summary
Isle Of Calm is a BMC-sanctioned project by Sunrise Housing in Powai, Mumbai 400076, registered with MahaRERA as 2 phases (P51800077401, P51800077922). The first phase was launched in August 2024. Together the phases have 320 units in 2 buildings: 318 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is March 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 36% complete and final finishes 0% complete. Neither phase has its structure complete.
217 units booked out of total 320 units (68%). Since the July 2026 update, 50 more units have been booked.