Elysia, Versova
by Olive Developers · Versova, Mumbai 400061 · Map
- Launched
- Oct 20243 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 7 of 1070% · 5 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 10 units
Rehab5 units for existing members
Land-owner share6 units, not for sale
Total 21 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 1
- 2 BHK
- 10
- 3 BHK
- 9
- Total units
- 21
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 10
- Rehab units
- 5
- Land-owner share (not for sale)
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 7 | |
| 100% | 100% | 25% | 5 | |
| 100% | 62% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Elysia by Olive Developers is a 21-unit BMC-sanctioned project in Versova, Mumbai 400061, launched in October 2024 with possession due in December 2027. 7 units booked out of 10 units for sale. The concrete structure (RCC) is complete.
Read full summary
Elysia is a BMC-sanctioned project by Olive Developers in Versova, Mumbai 400061, registered with MahaRERA as P51800077562. It was launched in October 2024. It has 21 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 10 are for sale, 5 are rehab units for existing members and 6 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete.
7 units booked out of 10 units for sale (70%). Since the July 2026 update, 2 more units have been booked.