Opulence, Goregaon West
by Ariha Buildtech LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- Oct 20245 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 1%Mid-construction
- Booked (free sale)
- 356 of 47375% · 531 rehab units
- Buildings
- 31.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale356 booked out of 473 units
Rehab531 units for existing members
Total 1,004 units. Rehab units are not for sale.
Project facts
- 1 RK
- 12
- 1 BHK
- 847
- 2 BHK
- 135
- Other units
- 10
- Total units
- 1,004
- Buildings
- 3
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 473
- Rehab units
- 531
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 1% | 0% | 356 | |
| 67% | 1% | 0% | 356 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Opulence by Ariha Buildtech LLP is a 1,004-unit SRA-sanctioned project in Goregaon West, Mumbai 400104, launched in October 2024 with possession due in December 2029. 356 units booked out of 473 units for sale. The concrete structure (RCC) is 1% complete.
Read full summary
Opulence is an SRA-sanctioned project by Ariha Buildtech LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800077572. It was launched in October 2024. It has 1,004 units in 3 buildings: 994 homes (1 RK, 1 BHK and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 1,004 units, 473 are for sale and 531 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation 67% complete, structure (RCC) 1% complete, final finishes not started.
356 units booked out of 473 units for sale (75%).
Ariha's track record in Mumbai
MahaRERA projects registered 2024–2026 in Mumbai
| Projects registered with MahaRERA | 4 |
|---|---|
| Total units across these projects | 1,171 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 4 |
| Possession date extended on the builder's application | 0 |
| MahaRERA complaints (filed by or against the builder), all Ariha projects | 0 (0 of 4 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.