Pramukh Shriniket Apartments, Vile Parle West
by Pramukh Associates · Vile Parle West, Mumbai 400056 · Map
- Launched
- Oct 20242 yrs 1 mth originally promised
- Possession (MahaRERA)
- Nov 2031Extended by 5 yrs
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 0 of 60% · 15 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 6 units
Rehab15 units for existing members
Total 21 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 4
- 2 BHK
- 7
- 3 BHK
- 10
- Total units
- 21
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 6
- Rehab units
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 0 | |
| 100% | 60% | 0% | 0 | |
| 100% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400056
Projects with 10–50 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 1 mth | 2 yrs 10 mths |
| Possession date extended | By 5 yrs | 0 of 3 |
| Possession date (MahaRERA) | Nov 2031 | May 2028 |
| Concrete structure (RCC) | 100% | 67% |
| Units booked (free sale) | 0% | 35% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Marble Saroj 56, Vile Parle West
- Mesacon Bliss, Vile Parle West
- The Alka Co-Operative Housing Society Limited, Vile Parle West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Marble Saroj 56 | June 2025 | May 2030 | 100% | 6 units booked out of 17 units for sale |
| Mesacon Bliss | July 2025 | May 2028 | 67% | 6 units booked out of 7 units for sale |
| The Alka Co-Operative Housing Society Limited | August 2025 | April 2027 | 60% | 0 units booked out of 10 units for sale |
About this project
Pramukh Shriniket Apartments by Pramukh Associates is a 21-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in October 2024 with possession due in November 2031. 0 units booked out of 6 units for sale. The concrete structure (RCC) is complete.
Read full summary
Pramukh Shriniket Apartments is a BMC-sanctioned project by Pramukh Associates in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800077689. It was launched in October 2024. It has 21 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 6 are for sale and 15 are rehab units for existing members.
Its registered possession date is November 2031, extended by 5 years from the original November 2026. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
0 units booked out of 6 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 100%.