Skyline Business World, Andheri East
by Skyline Prashasti · Andheri East, Mumbai 400059 · Map
- Launched
- Oct 2024First of 2 phases
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 97%Weighted across 2 phases
- Booked
- 453 of 51288%
- Buildings
- 24.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 512
- Total units
- 512
- Buildings
- 2
- Land
- 4.3 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Skyline Business World Wing C Nearing possession | P51800077710 | 0 | 100% | 97% | |
| Skyline Business World Wing B Mid-construction | PC1180002501134 | 0 | 69% | 0% |
Show updates by phase
Skyline Business World Wing C (P51800077710)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 453 | |
| 100% | 100% | 20% | 453 | |
| 100% | 0% | 0% | 242 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Skyline Business World Wing B (PC1180002501134)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 69% | 0% | 0 | |
| 100% | 46% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Skyline Business World by Skyline Prashasti is a 512-unit BMC-sanctioned project in Andheri East, Mumbai 400059, registered with MahaRERA in 2 phases, with possession due in March 2029. 453 units booked out of total 512 units. The concrete structure (RCC) is 97% complete.
Read full summary
Skyline Business World is a BMC-sanctioned project by Skyline Prashasti in Andheri East, Mumbai 400059, registered with MahaRERA as 2 phases (P51800077710, PC1180002501134). The first phase was launched in October 2024. Together the phases have 512 units in 2 buildings, as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is March 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 97% complete and final finishes 18% complete. Neither phase has its structure complete.
453 units booked out of total 512 units (88%).