Skip to main content

Siddha Niwas, Vile Parle West

by Praneeta Builders and Developers LLP · Vile Parle West, Mumbai 400056 · Map

Launched
Oct 20243 yrs 2 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
5
3 BHK
4
Other units
2
Total units
11
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 20%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%–
20%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Siddha Niwas by Praneeta Builders and Developers LLP is an 11-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in October 2024 with possession due in December 2027. Work on the concrete structure (RCC) has not started.

Read full summary

Siddha Niwas is a BMC-sanctioned project by Praneeta Builders and Developers LLP in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800077738. It was launched in October 2024. It has 11 units in 1 building: 9 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.