Empire Fairmont, Borivali West
by Empire Realty · Borivali West, Mumbai 400103 · Map
- Launched
- Nov 20242 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 29 of 3681% · 22 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale29 booked out of 36 units
Rehab22 units for existing members
Total 58 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 36
- 3 BHK
- 5
- Total units
- 58
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 36
- Rehab units
- 22
- Reserved units
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 29 | |
| 100% | 75% | 0% | 25 | |
| 100% | 30% | 0% | 20 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400103
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 1 mth | 3 yrs 9 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Sep 2028 |
| Concrete structure (RCC) | 100% | 72% |
| Units booked (free sale) | 81% | 63% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Questend Co Op Housing Society Ltd, Borivali West
- Romell Ariana, Borivali West
- Silverine Chsl, Borivali West
- 103 West, Borivali West
- The Erica, Borivali West
- White Orchid Residency, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Questend Co Op Housing Society Ltd | January 2025 | December 2027 | 0% | – |
| Romell Ariana | September 2024 | December 2028 | 100% | 12 units booked out of total 110 units |
| Silverine Chsl | February 2025 | May 2028 | 45% | 31 units booked out of 46 units for sale |
| 103 West | June 2024 | March 2029 | 100% | 42 units booked out of 64 units for sale |
| The Erica | May 2024 | March 2028 | 100% | 19 units booked out of 30 units for sale |
| White Orchid Residency | May 2025 | March 2030 | 45% | 37 units booked out of total 82 units |
About this project
Empire Fairmont by Empire Realty is a 58-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in November 2024 with possession due in December 2026. 29 units booked out of 36 units for sale. The concrete structure (RCC) is complete.
Read full summary
Empire Fairmont is a BMC-sanctioned project by Empire Realty in Borivali West, Mumbai 400103, registered with MahaRERA as P51800077872. It was launched in November 2024. It has 58 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 36 are for sale and 22 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.
29 units booked out of 36 units for sale (81%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 75% to 100%.
Empire Realty's track record in Mumbai
MahaRERA projects registered 2022–2026 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 690 |
| Completed without extending the possession date | 6 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 6 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 2 years |
| MahaRERA complaints (filed by or against the builder), all Empire Realty projects | 0 (0 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.