The Arcadian, Juhu
by Dhyan Projects Private Limited · Juhu, Mumbai 400049 · Map
- Launched
- Nov 20243 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 58%Mid-construction
- Booked (free sale)
- 42 of 9345% · 31 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale42 booked out of 93 units
Rehab31 units for existing members
Total 124 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 3 BHK
- 62
- 4 BHK
- 61
- Total units
- 124
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 93
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 58% | 0% | 42 | |
| 100% | 6% | 0% | 37 | |
| 100% | 0% | 0% | 0 | |
| 80% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400049
Projects with 60–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 1 mth | 3 yrs 7 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2027 |
| Concrete structure (RCC) | 58% | 15% |
| Units booked (free sale) | 45% | 40% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Spectrum Life, Juhu
- Kalpataru Amare, Juhu
- Gurukrupa Alaknanda, Juhu
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Spectrum Life | January 2025 | December 2028 | 15% | 14 units booked out of 40 units for sale |
| Kalpataru Amare | May 2024 | December 2027 | 0% | 45 units booked out of 81 units for sale |
| Gurukrupa Alaknanda | November 2023 | December 2026 | 100% | 19 units booked out of 47 units for sale |
About this project
The Arcadian by Dhyan Projects Private Limited is a 124-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in November 2024 with possession due in December 2027. 42 units booked out of 93 units for sale. The concrete structure (RCC) is 58% complete.
Read full summary
The Arcadian is a MHADA-sanctioned project by Dhyan Projects Private Limited in Juhu, Mumbai 400049, registered with MahaRERA as P51800077876. It was launched in November 2024. It has 124 units in 2 buildings, with 1, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 124 units, 93 are for sale and 31 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 58% complete, final finishes not started.
42 units booked out of 93 units for sale (45%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 6% to 58%.