Notan House, Vile Parle West

by Notan House Private Limited · Vile Parle West, Mumbai 400056 · Map

Launched
Nov 20242 yrs 4 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Nearing possession
Booked
31 of 4078%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
40
Total units
40
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%31
100%80%0%31
100%0%0%26
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Notan House by Notan House Private Limited is a 40-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in November 2024 with possession due in March 2027. 31 units booked out of total 40 units. The concrete structure (RCC) is complete.

Read full summary

Notan House is a BMC-sanctioned project by Notan House Private Limited in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800077910. It was launched in November 2024. It has 40 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

31 units booked out of total 40 units (78%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 80% to 100%.