Notan House, Vile Parle West
by Notan House Private Limited · Vile Parle West, Mumbai 400056 · Map
- Launched
- Nov 20242 yrs 4 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 31 of 4078%
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 40
- Total units
- 40
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 31 | |
| 100% | 80% | 0% | 31 | |
| 100% | 0% | 0% | 26 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Notan House by Notan House Private Limited is a 40-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in November 2024 with possession due in March 2027. 31 units booked out of total 40 units. The concrete structure (RCC) is complete.
Read full summary
Notan House is a BMC-sanctioned project by Notan House Private Limited in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800077910. It was launched in November 2024. It has 40 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
31 units booked out of total 40 units (78%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 80% to 100%.