ArtHouse, Bandra West

by Supreme Sky Ventures Private Limited · Bandra West, Mumbai 400050 · Map

Launched
Nov 20244 yrs 4 mths promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
9 of 1182%
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale9 booked out of 11 units

Land-owner share17 units, not for sale

Total 28 units. Land-owner units are not for sale.

Project facts

1 BHK
1
2 BHK
3
3 BHK
2
4 BHK
15
5+ BHK
7
Total units
28
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
11
Land-owner share (not for sale)
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 70%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%9
100%0%0%8
70%0%0%8
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400050

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths3 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2029Mar 2028
Concrete structure (RCC)0%75%
Units booked (free sale)82%68%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

ArtHouse by Supreme Sky Ventures Private Limited is a 28-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in November 2024 with possession due in March 2029. 9 units booked out of 11 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

ArtHouse is a BMC-sanctioned project by Supreme Sky Ventures Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as P51800077967. It was launched in November 2024. It has 28 units in 1 building, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 11 are for sale and 17 are the land-owner's share, not for sale.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

9 units booked out of 11 units for sale (82%). Since the July 2026 update, 1 more unit has been booked.