Chandak Sarvam, Andheri East

by Chandak Realtors Private Limited · Andheri East, Mumbai 400059 · Map

Launched
Nov 20246 yrs 1 mth promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
12%Mid-construction
Booked
126 of 29443% · 107 in Jul 2026
Buildings
60.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
127
3 BHK
128
4 BHK
39
Total units
294
Buildings
6
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Reserved units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)12%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 50%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 12%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 12%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%12%0%126
50%0%0%107
100%0%0%77
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Chandak Sarvam by Chandak Realtors Private Limited is a 294-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in November 2024 with possession due in December 2030. 126 units booked out of total 294 units. The concrete structure (RCC) is 12% complete.

Read full summary

Chandak Sarvam is a BMC-sanctioned project by Chandak Realtors Private Limited in Andheri East, Mumbai 400059, registered with MahaRERA as P51800078249. It was launched in November 2024. It has 294 units in 6 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation 50% complete, structure (RCC) 12% complete, final finishes not started.

126 units booked out of total 294 units (43%). Since the July 2026 update, 19 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 12%.

Chandak's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA6
Total units across these projects3,625
Completed without extending the possession date1
Completed after an extension0
Lapsed0
Under construction5
Possession date extended on the builder's application0
MahaRERA complaints (filed by or against the builder), all Chandak projects10 (3 of 6 projects)

See all Chandak projects →