Siddhi Darshan, Dadar West

by Mighty Engineers Developers & Contractors LLP · Dadar West, Mumbai 400028 · Map

Launched
Dec 20245 yrs promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
7 of 3719% · 111 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 37 units

Rehab111 units for existing members

Total 148 units. Rehab units are not for sale.

Project facts

1 BHK
108
2 BHK
16
3 BHK
16
4 BHK
2
Other units
6
Total units
148
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
37
Rehab units
111

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%7
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Siddhi Darshan by Mighty Engineers Developers & Contractors LLP is a 148-unit SRA-sanctioned project in Dadar West, Mumbai 400028, launched in December 2024 with possession due in December 2029. 7 units booked out of 37 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Siddhi Darshan is an SRA-sanctioned project by Mighty Engineers Developers & Contractors LLP in Dadar West, Mumbai 400028, registered with MahaRERA as P51800078264. It was launched in December 2024. It has 148 units in 2 buildings: 142 homes (1, 2, 3 and 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 148 units, 37 are for sale and 111 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

7 units booked out of 37 units for sale (19%).