Brahma Aashirvad, Borivali West
by M/s Brahma Realtors · Borivali West, Mumbai 400092 · Map
- Launched
- Dec 20241 yr 2 mths originally promised
- Possession (MahaRERA)
- May 2027Extended by 1 yr 3 mths
- Concrete structure
- 42%Mid-construction
- Booked (free sale)
- 1 of 617% · 12 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 6 units
Rehab12 units for existing members
Total 18 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 5
- 2 BHK
- 5
- Other units
- 8
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 42% | 0% | 1 | |
| 50% | 21% | 0% | 1 | |
| 0% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400092
Projects with up to 20 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 2 mths | 2 yrs 11 mths |
| Possession date extended | By 1 yr 3 mths | 0 of 3 |
| Possession date (MahaRERA) | May 2027 | Sep 2027 |
| Concrete structure (RCC) | 42% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Modispaces Nile, Borivali West
- Trilogy Vithal Co-Operative Housing Society Limited, Borivali West
- Gautam Prabhu, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Modispaces Nile | October 2024 | September 2027 | 100% | 4 units booked out of total 13 units |
| Trilogy Vithal Co-Operative Housing Society Limited | February 2025 | December 2027 | 40% | – |
| Gautam Prabhu | May 2024 | April 2027 | 100% | 4 units booked out of 6 units for sale |
About this project
Brahma Aashirvad by M/s Brahma Realtors is an 18-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in December 2024 with possession due in May 2027. 1 unit booked out of 6 units for sale. The concrete structure (RCC) is 42% complete.
Read full summary
Brahma Aashirvad is a BMC-sanctioned project by M/s Brahma Realtors in Borivali West, Mumbai 400092, registered with MahaRERA as P51800078278. It was launched in December 2024. It has 18 units in 1 building: 10 homes (1 and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 6 are for sale and 12 are rehab units for existing members.
Its registered possession date is May 2027, extended by 1 year 3 months from the original February 2026. Construction: excavation complete, structure (RCC) 42% complete, final finishes not started.
1 unit booked out of 6 units for sale (17%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 21% to 42%.