Sayba Elysia, Kurla West
by Sayba Home Makers · Kurla West, Mumbai 400070 · Map
- Launched
- Dec 20242 yrs 7 mths promised
- Possession (MahaRERA)
- Jul 2027Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 63 of 11057% · 216 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale63 booked out of 110 units
Rehab216 units for existing members
Total 326 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 295
- 2 BHK
- 14
- Other units
- 17
- Total units
- 326
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 110
- Rehab units
- 216
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 63 | |
| 100% | 90% | 0% | 50 | |
| 100% | 80% | 0% | 47 | |
| 100% | 5% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sayba Elysia by Sayba Home Makers is a 326-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in December 2024 with possession due in July 2027. 63 units booked out of 110 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Sayba Elysia is a BMC-sanctioned project by Sayba Home Makers in Kurla West, Mumbai 400070, registered with MahaRERA as P51800078321. It was launched in December 2024. It has 326 units in 2 buildings: 309 homes (1 and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 326 units, 110 are for sale and 216 are rehab units for existing members.
Its registered possession date is July 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
63 units booked out of 110 units for sale (57%). Since the July 2026 update, 13 more units have been booked.