Meher Villa, Khar West

by Hansganga Hari Shewa Developers Private Limited · Khar West, Mumbai 400052 · Map

Launched
Dec 20243 yrs 3 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
10 of 10100%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 10 units

Land-owner share8 units, not for sale

Total 18 units. Land-owner units are not for sale.

Project facts

1 BHK
10
2 BHK
1
3 BHK
3
Other units
4
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Reserved units
10
Free-sale units
10
Land-owner share (not for sale)
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%10
100%70%0%10
100%0%0%10
90%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400052

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths3 yrs
Possession date extendedNo0 of 3
Possession date (MahaRERA)Mar 2028Dec 2027
Concrete structure (RCC)70%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Meher Villa by Hansganga Hari Shewa Developers Private Limited is an 18-unit SRA-sanctioned project in Khar West, Mumbai 400052, launched in December 2024 with possession due in March 2028. 10 units booked out of 10 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

Meher Villa is an SRA-sanctioned project by Hansganga Hari Shewa Developers Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51800078336. It was launched in December 2024. It has 18 units in 1 building: 14 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 10 are for sale and 8 are the land-owner's share, not for sale.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

10 units booked out of 10 units for sale (100%).