Keva, Ghatkopar East
by Pinal Realty LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Dec 20242 yrs 11 mths promised
- Possession (MahaRERA)
- Nov 2027Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 18 of 2864% · 6 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale18 booked out of 28 units
Rehab6 units for existing members
Land-owner share7 units, not for sale
Total 41 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 8
- 1 BHK
- 1
- 2 BHK
- 1
- 3 BHK
- 15
- 4 BHK
- 14
- Other units
- 2
- Total units
- 41
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 28
- Rehab units
- 6
- Land-owner share (not for sale)
- 7
- Reserved units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 18 | |
| 100% | 100% | 0% | 31 | |
| 0% | 0% | 0% | 31 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400077
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 2 yrs 10 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Nov 2027 | Oct 2027 |
| Concrete structure (RCC) | 80% | 100% |
| Units booked (free sale) | 64% | 53% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Dotom Jewel, Ghatkopar East
- Sky Casa, Ghatkopar East
- Manju Apartment Chs, Ghatkopar East
- Aum Laxminarayan, Ghatkopar East
- Om Shreepal, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dotom Jewel | December 2024 | October 2027 | 96% | 23 units booked out of 49 units for sale |
| Sky Casa | November 2024 | December 2028 | 100% | 15 units booked out of 15 units for sale |
| Manju Apartment Chs | November 2024 | April 2027 | 100% | 8 units booked out of 15 units for sale |
| Aum Laxminarayan | November 2024 | December 2027 | 100% | 0 units booked out of 33 units for sale |
| Om Shreepal | July 2024 | December 2026 | 100% | 13 units booked out of 15 units for sale |
About this project
Keva by Pinal Realty LLP is a 41-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2024 with possession due in November 2027. 18 units booked out of 28 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Keva is a BMC-sanctioned project by Pinal Realty LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800078612. It was launched in December 2024. It has 41 units in 1 building: 39 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 41 units, 28 are for sale, 6 are rehab units for existing members and 7 are the land-owner's share, not for sale.
Its registered possession date is November 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
18 units booked out of 28 units for sale (64%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 100% to 80%.