Rehmaniya Apartments, Kurla West
by S & S Enterprises · Kurla West, Mumbai 400070 · Map
- Launched
- Jan 20251 yr 11 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 71%Mid-construction
- Booked (free sale)
- 42 of 4789% · 36 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale42 booked out of 47 units
Rehab36 units for existing members
Total 83 units. Rehab units are not for sale.
Project facts
- 1 RK
- 69
- 1 BHK
- 8
- 2 BHK
- 6
- Total units
- 83
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 47
- Rehab units
- 36
- Reserved units
- 28
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 71% | 0% | 42 | |
| 100% | 71% | 0% | 42 | |
| 100% | 71% | 0% | 42 | |
| 100% | 71% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Rehmaniya Apartments by S & S Enterprises is an 83-unit SRA-sanctioned project in Kurla West, Mumbai 400070, launched in January 2025 with possession due in December 2026. 42 units booked out of 47 units for sale. The concrete structure (RCC) is 71% complete.
Read full summary
Rehmaniya Apartments is an SRA-sanctioned project by S & S Enterprises in Kurla West, Mumbai 400070, registered with MahaRERA as P51800078660. It was launched in January 2025. It has 83 units in 2 buildings, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 83 units, 47 are for sale and 36 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 71% complete, final finishes not started.
42 units booked out of 47 units for sale (89%).