Damji Shamji Avenuee, Ghatkopar East
by OV Buildcon LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Jan 20254 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 23 of 6337% · 26 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale23 booked out of 63 units
Rehab26 units for existing members
Land-owner share7 units, not for sale
Total 96 units. Rehab and land-owner units are not for sale.
Project facts
- Other units
- 96
- Total units
- 96
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 63
- Rehab units
- 26
- Land-owner share (not for sale)
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 90% | 0% | 0% | 23 | |
| 90% | 0% | 0% | 6 | |
| 90% | 0% | 0% | 6 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Damji Shamji Avenuee by OV Buildcon LLP is a 96-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in January 2025 with possession due in December 2029. 23 units booked out of 63 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Damji Shamji Avenuee is a BMC-sanctioned project by OV Buildcon LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800078783. It was launched in January 2025. It has 96 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 96 units, 63 are for sale, 26 are rehab units for existing members and 7 are the land-owner's share, not for sale.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.
23 units booked out of 63 units for sale (37%). Since the July 2026 update, 17 more units have been booked.