- Launched
- Jan 20252 yrs 2 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 2 of 922% · 7 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 9 units
Rehab7 units for existing members
Total 16 units. Rehab units are not for sale.
Project facts
- 3 BHK
- 15
- Other units
- 1
- Total units
- 16
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 2 | |
| 100% | 100% | 0% | 2 | |
| 100% | 82% | 0% | 2 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Horizon View by I.R.Developers LLP is a 16-unit BMC-sanctioned project in Andheri East, Mumbai 400093, launched in January 2025 with possession due in March 2027. 2 units booked out of 9 units for sale. The concrete structure (RCC) is complete.
Read full summary
Horizon View is a BMC-sanctioned project by I.R.Developers LLP in Andheri East, Mumbai 400093, registered with MahaRERA as P51800078821. It was launched in January 2025. It has 16 units in 1 building: 15 homes (3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 16 units, 9 are for sale and 7 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
2 units booked out of 9 units for sale (22%).