Lalani Goodwill Building No, Andheri East

by Lalani Constructions Private Limited · Andheri East, Mumbai 400059 · Map

Launched
Jan 2025First of 2 phases
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
54%Weighted across 2 phases
Booked (free sale)
25 of 6936% · 34 rehab units
Buildings
30.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 69 units

Rehab34 units for existing members

Total 103 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
72
3 BHK
22
Other units
1
Total units
103
Buildings
3
Land
0.5 acres
Phases
2
MahaRERA complaints
0
Free-sale units
69
Rehab units
34

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Lalani Goodwill Building No 2
Mid-construction
P51800078852990%0%
Lalani Goodwill Building No 1
Mid-construction
P518000790659350%27%
Show updates by phase

Lalani Goodwill Building No 2 (P51800078852)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%15%0
100%90%15%0
100%40%5%0
0%0%5%0

"–" means MahaRERA shows no figure for that update.

Lalani Goodwill Building No 1 (P51800079065)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%5%25
100%50%5%25
100%7%5%23

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)54%
Finishes, lifts and services6%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 54%Oct 2026: Concrete structure (RCC) 54%Dec 2025: Final finishes 5%Jul 2026: Final finishes 6%Oct 2026: Final finishes 6%Excavation 100%Concrete structure (RCC) 54%Final finishes 6%

How to read construction stages

About this project

Lalani Goodwill Building No by Lalani Constructions Private Limited is a 103-unit BMC-sanctioned project in Andheri East, Mumbai 400059, registered with MahaRERA in 2 phases, with possession due in June 2028. 25 units booked out of 69 units for sale. The concrete structure (RCC) is 54% complete.

Read full summary

Lalani Goodwill Building No is a BMC-sanctioned project by Lalani Constructions Private Limited in Andheri East, Mumbai 400059, registered with MahaRERA as 2 phases (P51800078852, P51800079065). The first phase was launched in January 2025. Together the phases have 103 units in 3 buildings: 102 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 103 units, 69 are for sale and 34 are rehab units for existing members.

The registered possession date is June 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 54% complete and final finishes 6% complete. Neither phase has its structure complete.

25 units booked out of 69 units for sale (36%).