Skip to main content

Vascon Orchids, Santacruz West

by Vascon Engineers Ltd · Santacruz West, Mumbai 400054 · Map

Launched
Jan 20253 yrs 8 mths promised
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
45%Mid-construction
Booked (free sale)
29 of 6445% · 48 rehab units
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale29 booked out of 64 units

Rehab48 units for existing members

Total 112 units. Rehab units are not for sale.

Project facts

2 BHK
64
3 BHK
46
Other units
2
Total units
112
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
64
Rehab units
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 10%Dec 2025: Excavation 10%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 30%Oct 2026: Concrete structure (RCC) 45%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%29
100%30%0%13
10%0%0%0
10%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vascon Orchids by Vascon Engineers Ltd is a 112-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in January 2025 with possession due in September 2028. 29 units booked out of 64 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

Vascon Orchids is a BMC-sanctioned project by Vascon Engineers Ltd in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800078870. It was launched in January 2025. It has 112 units in 1 building: 110 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 112 units, 64 are for sale and 48 are rehab units for existing members.

Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

29 units booked out of 64 units for sale (45%). Since the July 2026 update, 16 more units have been booked and the reported concrete structure (RCC) has gone from 30% to 45%.