Skip to main content

Ranbir Castle, Andheri East

by Ranbirdeep Realtors LLP · Andheri East, Mumbai 400093 · Map

Launched
Jan 20252 yrs 2 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
75%Mid-construction
Booked (free sale)
8 of 2433% · 15 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 24 units

Rehab15 units for existing members

Total 39 units. Rehab units are not for sale.

Project facts

2 BHK
31
3 BHK
8
Total units
39
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
24
Rehab units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 75%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%20%8
100%50%0%5
0%0%0%3
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ranbir Castle by Ranbirdeep Realtors LLP is a 39-unit BMC-sanctioned project in Andheri East, Mumbai 400093, launched in January 2025 with possession due in March 2027. 8 units booked out of 24 units for sale. The concrete structure (RCC) is 75% complete.

Read full summary

Ranbir Castle is a BMC-sanctioned project by Ranbirdeep Realtors LLP in Andheri East, Mumbai 400093, registered with MahaRERA as P51800078885. It was launched in January 2025. It has 39 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 39 units, 24 are for sale and 15 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes 20% complete.

8 units booked out of 24 units for sale (33%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 75%.