Golden Vista, Santacruz East
by Blue Diamond Spaces Private Limited · Santacruz East, Mumbai 400098 · Map
- Launched
- Jan 20254 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 23%Mid-construction
- Booked
- 67 of 17239% · 46 in Jul 2026
- Buildings
- 40.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 103
- 2 BHK
- 39
- 3 BHK
- 29
- Other units
- 1
- Total units
- 172
- Buildings
- 4
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 23% | 0% | 67 | |
| 100% | 0% | 0% | 46 | |
| 100% | 0% | 0% | 30 |
"–" means MahaRERA shows no figure for that update.
About this project
Golden Vista by Blue Diamond Spaces Private Limited is a 172-unit SRA-sanctioned project in Santacruz East, Mumbai 400098, launched in January 2025 with possession due in December 2029. 67 units booked out of total 172 units. The concrete structure (RCC) is 23% complete.
Read full summary
Golden Vista is an SRA-sanctioned project by Blue Diamond Spaces Private Limited in Santacruz East, Mumbai 400098, registered with MahaRERA as P51800078953. It was launched in January 2025. It has 172 units in 4 buildings: 171 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 23% complete, final finishes not started.
67 units booked out of total 172 units (39%). Since the July 2026 update, 21 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 23%.