Raya, Chembur

by F. A. Builders & Developers LLP · Chembur, Mumbai 400074 · Map

Launched
Feb 20254 yrs 10 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
36%Mid-construction
Booked
110 of 24844% · 62 in Jul 2026
Buildings
31.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
239
Other units
8
Total units
248
Buildings
3
Land
1.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation67%
Concrete structure (slabs)36%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 50%Jul 2026: Excavation 67%Oct 2026: Excavation 67%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 3%Oct 2026: Concrete structure (RCC) 36%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 67%Concrete structure (RCC) 36%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%36%0%110
67%3%0%62
50%0%0%29

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Raya by F. A. Builders & Developers LLP is a 248-unit SRA-sanctioned project in Chembur, Mumbai 400074, launched in February 2025 with possession due in December 2029. 110 units booked out of total 248 units. The concrete structure (RCC) is 36% complete.

Read full summary

Raya is an SRA-sanctioned project by F. A. Builders & Developers LLP in Chembur, Mumbai 400074, registered with MahaRERA as P51800079114. It was launched in February 2025. It has 248 units in 3 buildings: 240 homes (1 and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 67% complete, structure (RCC) 36% complete, final finishes not started.

110 units booked out of total 248 units (44%). Since the July 2026 update, 48 more units have been booked and the reported concrete structure (RCC) has gone from 3% to 36%.