Shreeji Nakshtra, Malad West

by Shreeji Construction · Malad West, Mumbai 400064 · Map

Launched
Feb 20253 yrs 6 mths promised
Possession (MahaRERA)
Aug 2028Not extended
Concrete structure
25%Mid-construction
Booked (free sale)
44 of 12336% · 92 rehab units
Buildings
20.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale44 booked out of 123 units

Rehab92 units for existing members

Total 215 units. Rehab units are not for sale.

Project facts

1 BHK
196
Other units
19
Total units
215
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
123
Rehab units
92

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 50%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 25%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 25%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%44
100%25%0%32
50%0%0%25

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shreeji Nakshtra by Shreeji Construction is a 215-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in February 2025 with possession due in August 2028. 44 units booked out of 123 units for sale. The concrete structure (RCC) is 25% complete.

Read full summary

Shreeji Nakshtra is an SRA-sanctioned project by Shreeji Construction in Malad West, Mumbai 400064, registered with MahaRERA as P51800079261. It was launched in February 2025. It has 215 units in 2 buildings: 196 homes (1 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 215 units, 123 are for sale and 92 are rehab units for existing members.

Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.

44 units booked out of 123 units for sale (36%). Since the July 2026 update, 12 more units have been booked.