Skip to main content

Adityaraj Greens, Powai

by Jbr Realtors LLP · Powai, Mumbai 400076 · Map

Launched
Feb 20253 yrs 10 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
26 of 8431% · 44 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale26 booked out of 84 units

Rehab44 units for existing members

Total 128 units. Rehab units are not for sale.

Project facts

1 BHK
66
2 BHK
31
3 BHK
31
Total units
128
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
84
Rehab units
44

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 20%Oct 2026: Concrete structure (RCC) 60%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%26
100%20%0%19
0%0%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Adityaraj Greens by Jbr Realtors LLP is a 128-unit BMC-sanctioned project in Powai, Mumbai 400076, launched in February 2025 with possession due in December 2028. 26 units booked out of 84 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Adityaraj Greens is a BMC-sanctioned project by Jbr Realtors LLP in Powai, Mumbai 400076, registered with MahaRERA as P51800079280. It was launched in February 2025. It has 128 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 128 units, 84 are for sale and 44 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

26 units booked out of 84 units for sale (31%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 20% to 60%.