Shubham Artesia, Ghatkopar East

by Avvad Realtty LLP · Ghatkopar East, Mumbai 400075 · Map

Launched
Mar 20252 yrs 9 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked
49 of 15931%
Buildings
20.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
18
3 BHK
118
Other units
22
Total units
159
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%49
100%0%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shubham Artesia by Avvad Realtty LLP is a 159-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in March 2025 with possession due in December 2027. 49 units booked out of total 159 units. Work on the concrete structure (RCC) has not started.

Read full summary

Shubham Artesia is a MHADA-sanctioned project by Avvad Realtty LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800079435. It was launched in March 2025. It has 159 units in 2 buildings: 137 homes (1, 2 and 3 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

49 units booked out of total 159 units (31%).