Shubham Artesia, Ghatkopar East
by Avvad Realtty LLP · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Mar 20252 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 0%Early stage
- Booked
- 49 of 15931%
- Buildings
- 20.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 18
- 3 BHK
- 118
- Other units
- 22
- Total units
- 159
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 49 | |
| 100% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
About this project
Shubham Artesia by Avvad Realtty LLP is a 159-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in March 2025 with possession due in December 2027. 49 units booked out of total 159 units. Work on the concrete structure (RCC) has not started.
Read full summary
Shubham Artesia is a MHADA-sanctioned project by Avvad Realtty LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800079435. It was launched in March 2025. It has 159 units in 2 buildings: 137 homes (1, 2 and 3 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
49 units booked out of total 159 units (31%).