Arave, Vile Parle West
by Jrt Realty LLP · Vile Parle West, Mumbai 400056 · Map
- Launched
- Mar 20253 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 55%Mid-construction
- Booked (free sale)
- 38 of 4290% · 30 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale38 booked out of 42 units
Rehab30 units for existing members
Total 72 units. Rehab units are not for sale.
Project facts
- 1 RK
- 10
- 1 BHK
- 7
- 2 BHK
- 21
- 3 BHK
- 29
- 4 BHK
- 5
- Total units
- 72
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 42
- Rehab units
- 30
- Reserved units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 0% | 38 | |
| 100% | 50% | 0% | 7 | |
| 0% | 0% | 0% | 7 |
"–" means MahaRERA shows no figure for that update.
About this project
Arave by Jrt Realty LLP is a 72-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in March 2025 with possession due in December 2028. 38 units booked out of 42 units for sale. The concrete structure (RCC) is 55% complete.
Read full summary
Arave is a BMC-sanctioned project by Jrt Realty LLP in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800079479. It was launched in March 2025. It has 72 units in 2 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 72 units, 42 are for sale and 30 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 55% complete, final finishes not started.
38 units booked out of 42 units for sale (90%). Since the July 2026 update, 31 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 55%.